QUESTION 1
Haqen
Food Industry Sdn Bhd is preparing its aggregate plan for the second half of
the year. The table below contains monthly demand estimates.
Month
|
Expected
Demand (units)
|
January
|
18,000
|
February
|
21,000
|
March
|
17,500
|
April
|
12,500
|
May
|
12,000
|
June
|
13,500
|
Production Time
|
:
|
10 minutes /
unit
|
Working hours
|
:
|
10 hours / day
|
Days per month
|
:
|
22 work days /
month
|
Current number
of workers
|
:
|
10 workers
|
Overtime
capacity
|
:
|
600 units per
month
|
Average labour
cost
|
:
|
RM10 / hour
|
Overtime cost
|
:
|
RM12 / hour
|
Subcontract cost
|
:
|
RM20 / unit
|
Inventory
Holding cost
|
:
|
RM0.50 / unit
per month
|
Beginning
Inventory
|
:
|
800 units
|
Management
prefers to keep a constant workforce and production level, absorbing variations
through inventory excesses, overtime and subcontract. Demand not met will be
outsourced to its sister company. Develop an aggregate plan and compute the
total cost that will meet the demand and other conditions of the problem.
(11 marks)
Answer:
For a worker
à 1 unit = 10 minutes
à 1 hour = 60 minutes / 10
minutes = 6 units / hour
à 1 day = 10 hours X 6
units = 60 units / day
à 1 month = 60 units X 22
days = 1,320 units / month
Therefore, for 10 workers
à 1,320 units X 10 workers
= 13,200 units
(1 mark)
|
Month
|
Demand
|
Actual Prod
|
Inv Change
|
Beginning stock
|
Overtime
|
Subcontract
|
End inv
|
|
January
|
18,000
|
13,200
|
-4,800
|
800
|
600
|
3,400
|
|
|
February
|
21,000
|
13,200
|
-7,800
|
|
600
|
7,200
|
|
|
March
|
17,500
|
13,200
|
-4,300
|
|
600
|
3,700
|
|
|
April
|
12,500
|
13,200
|
700
|
|
-
|
-
|
700
|
|
May
|
12,000
|
13,200
|
1,200
|
700
|
-
|
-
|
1,900
|
|
June
|
13,500
|
13,200
|
-300
|
1,900
|
-
|
-
|
1,600
|
|
|
94,500
|
79,200
|
|
|
1,800
|
14,300
|
4,200
|
|
Marks given
|
|
(1 mark)
|
|
|
(1 mark)
|
(1 mark)
|
(1 mark)
|
|
|
|
|
|
|
|
|
|
|
|
Total cost for the plan
1)
Regular cost
= Total unit produced X
cost per hour
= 79,200 units / 6
unit per hour X RM10 per hour
= RM132,000 (1
mark)
2)
Overtime cost
= 1,800 units / 6 unit per hour X RM12 per
hour
= RM3,600
(1 mark)
3)
Subcontract cost
= 14,300 units X RM20 per
unit
= RM28,600
(1
mark)
4)
Inventory holding cost
= 4,200 units X RM0.5.
per unit per month
= RM2,100
(1 mark)
5)
Therefore, Total cost
= RM132,000 + RM3,600 +
RM28,600 + RM2,100
= RM166,300
(2 marks)
|
|||||||
QUESTION 2
Discuss the
three (3) phases of project management. Support your answer by relevant
examples.
(9
marks)
Answer:
1)
Project planning
2)
Project scheduling
3)
Project control
Students
are required to discuss on these three points. Answer must be supported by
relevant examples.
(any four points X 5 marks = 20 marks)
|